Industrial Production Process of Steel Structure Products
1. Project Planning & Design Phase
1.1 Design Parameter Standardization
- Load calculations: Wind load (0.5-1.5kN/m² per GB 50009), seismic grade (6-8度设防)
- Connection design: Bolted joints (10.9S grade) with slip factor ≥0.35
- Modeling software: Tekla Structures (公差±0.1mm), BIM collision detection
1.2 Material Specification
- Steel plate selection:
- Thickness range: 6-100mm (Q355B yield strength ≥355MPa)
- Zinc coating: 275g/m² for C3 corrosion environment
- Supplementary materials:
- Welding wire: ER50-6 (AWS A5.18 standard)
- Paint systems: 3-coat epoxy-polyurethane (DFT 280μm)
2. Precision Manufacturing Process
2.1 Cutting Technology Matrix
| Method | Tolerance | Kerf Width | Application |
|---|---|---|---|
| Plasma | ±1.2mm | 3-5mm | Thickness >25mm |
| Laser | ±0.3mm | 0.2-1mm | Precision joints |
| Waterjet | ±0.5mm | 0.8-1.2mm | Composite materials |
2.2 Welding Quality Control
- Procedure qualification:
- Preheat temp: 100-150℃ (t≥25mm)
- Interpass temp: ≤230℃
- NDT methods:
- UT: Level B scanning (defect ≤Φ3mm)
- RT: Class II per EN ISO 5817
3. Automated Assembly System
3.1 Robotic Fabrication
- Positioning accuracy: ±0.05mm (6-axis robots)
- Clamping force: 5-20kN (vacuum/pneumatic)
- In-process inspection: 3D laser scanning (0.02mm resolution)
3.2 Modular Construction
- Unit weight limit: ≤50 tons (road transport)
- Interface tolerance:
- Bolt holes: ±1.0mm
- Shear connectors: ±2mm vertical
4. Advanced Coating Process
4.1 Surface Preparation
- Blasting profile:
- Angular anchor pattern (40-75μm)
- Soluble salt limit: ≤20mg/m² NaCl
- Environmental controls:
- Air dew point: ≤3℃ above substrate
- Relative humidity: 40-60%
4.2 Curing Parameters
- Infrared curing:
- Peak metal temp: 80-100℃
- Exposure time: 8-12 minutes
- Adhesion test: ≥5MPa (ISO 4624 cross-cut)
5. Digital Quality Assurance
5.1 IoT Monitoring
- Weld tracking:
- Arc voltage: 28±2V
- Wire feed speed: 8-12m/min
- Coating thickness:
- Continuous measurement (XRF technology)
- Data logging per ISO 19840
5.2 Blockchain Documentation
- Material traceability:
- QR code tracking (from mill to site)
- Automated MTC verification
- Non-conformance management:
- RFID tagging for quarantine parts
- Automated alert system